Progress continued in June as follows:
- June 2, 2005 - Hilliard Adopt-A-House marked the deck for wall placement and verified/corrected pre-built first floor walls.
- June 4, 2005 - Hilliard Adopt-A-House raised most of the first floor walls.
- June 8, 2005 - Hilliard Adopt-A-House finished first floor wall raising, erected back porch beams and put on one-half of the cap plates.
- June 11, 2005 - Hilliard Adopt-A-House put the
OSB on first floor band boards, finished first floor cap plates, put up second floor band boards, framed in the stairway, and put in second floor joists.
- June 15, 2005 - Hilliard Adopt-A-House plus Nationwide volunteers completed second floor joists and began decking.
- June 17, 2005 - Hilliard Adopt-A-House led Nationwide volunteers finishing the deck.<.li>
- June 18, 2005 - Held "Wall Raising Ceremony" followed by Hilliard Adopt-A-House erecting second floor exterior walls and front porch beams.
- June 22, 2005 - Hilliard Adopt-A-House raised second floor interior walls and corrected one exterior wall.
- June 23, 2005 - Hilliard Adopt-A-Houseled Nationwide volunteers putting on the second floor cap plates and prepping the trusses.
- June 24, 2005 - Hilliard Adopt-A-House braced second floor walls and marked for truss placement.
- June 25, 2005 - Hilliard Adopt-A-House raised the trusses, laid one-half of the roof sheathing, erected porch posts and installed kitchen deadwood.
- June 29, 2005 - Hilliard Adopt-A-House finished the roof sheathing and hung hurricane clips, and contractors poured the garage foundation walls.